Use this soil swell factor calculator to convert excavation volumes between bank (in-place), loose (hauled) and compacted (placed fill) states, see your load and shrink factors, and count how many truck loads a job needs.
Pick a soil type to load typical swell and shrinkage percentages, or choose Custom and type your own from a geotechnical report or past jobs. Select which volume you already know (bank, loose or compacted), enter it, and add your truck capacity if you want a load count. The calculator returns all three volumes, the swell, load and shrink factors, a rounded-up truck count, and a table showing how the answer shifts if your swell estimate is a few points off.
Dirt does not occupy the same space after you dig it. A cubic yard of clay in the ground can become about 1.4 cubic yards once it is loosened and loaded, because digging breaks the soil structure and opens air voids. Ignore that and you under-order trucks, under-size stockpile areas and blow your haul budget. A 40 × 30 ft basement dug 8 ft deep is roughly 356 bank yards, but at 25% swell you are actually moving about 444 loose yards, which is the difference between 30 loads and 38 loads.
The same physics works in reverse when you import fill. Compacting soil squeezes those voids out, so a yard of loose borrow material rarely yields a full yard of finished fill. If a spec calls for 100 compacted yards behind a retaining wall, you may need 140 or more loose yards delivered. Excavation contractors, site-work estimators, landscapers, homeowners planning a pond or grading project, and anyone ordering fill or hauling spoil use these factors. Getting them right early protects schedules and prevents the all-too-common "we're short a few loads" call.
Earthmoving uses three volume states. Bank (BCY or BCM) is soil undisturbed in place. Loose (LCY or LCM) is soil after excavation. Compacted (CCY or CCM) is soil after it is placed and compacted. The calculator follows the standard bank/loose/compacted convention used in equipment-manufacturer performance handbooks, and compaction targets are normally verified against ASTM D698 or D1557 density tests. Local specifications and soil conditions vary.
If you know the loose volume, the calculator divides by (1 + swell) to get bank. If you know the compacted volume, it divides by (1 − shrink). Shrinkage here is measured from the original bank volume, not from the loose volume. Truck loads and the planning volume are always rounded up to the next whole number, so the estimate errs on the side of having enough capacity rather than too little.
You are excavating a basement 40 ft × 30 ft × 8 ft deep in common earth.
Enter 355.56 as bank volume with those settings and the tool shows the same figures. Now reverse it: to build 100 compacted yards of fill, divide by 0.88 to get 113.64 bank yards, which equals 142.05 loose yards to deliver.
It is the ratio by which soil increases in volume when excavated, shown as a percentage. A 25% swell means 1 bank yard becomes 1.25 loose yards. It depends on soil type, moisture and how finely the material is broken up.
Swell factor is the percentage volume increase (1 + swell%), while load factor is its reciprocal, 1 ÷ (1 + swell%). Load factor converts loose volume back to bank volume. For 25% swell the load factor is 0.800.
Multiply the bank volume by (1 + swell%). For 200 bank yards of clay at 40% swell, 200 × 1.40 = 280 loose yards. Select "Bank" in the calculator and enter 200 to see this directly.
Shrink factor is compacted volume divided by bank volume, which is 1 minus the shrinkage percentage. A 12% shrinkage gives a factor of 0.88, so 100 bank yards compact to about 88 yards. Required compaction level, set by your project spec, strongly affects the result.
Convert the bank volume to loose volume, then divide by the truck's loose capacity and round up. For 444.45 loose yards and a 12-yard truck, you need 38 loads. Add extra for contingency if conditions are uncertain.
No. It is a planning estimate based on typical values and standard formulas. Confirm swell, shrinkage and compaction requirements with your geotechnical report, project specifications and local authorities.